Status of Working Plan in Uttarakhand

 


S.No
Name of Forest Division Duration of WP Status of WP Name of Officer Remarks
1 Tons 2005-06 to 2014-15   Expired   The posting of WPO is awaited
2 Uttarkashi 2006-07 to 2015-16 Expired   Draft WP(2016-17 to 2025-26 ) submitted to GoI & circulated to all members of Standing Consultative Committee for their comments
3 Haldwani 2006-07 to 2015-17 Expired   Final Draft WP(2016-17 to 20125-26) submitted to GoI
4 Tarai East 2006-07 to 2015-18 Expired   Final Draft WP(2016-17 to 20125-26) submitted to GoI
5 Almora 2006-07 to 2015-19 Expired   The posting of WPO is awaited
6 Chakrata 2007-08 to2016-17 Expired   WP revision/prepration work is in progress for period 2017-18 to 2026-27
7 Nainital 2008-09 to 2017-18 Expired   WP revision/prepration work is in progress for period 2018-19 to 2027-28
8 Ramnagar 2008-09 to 2017-18 Approved   WP revision/prepration work is in progress for period 2018-19 to 2027-28
9 Dehradun 2009-10 to 2018-19 Approved   The posting of WPO is awaited
10 Soil conservation Kalsi 2009-10 to 2018-19 Approved   WP revision/prepration work is in progress for period 2019-20 to 2028-29
11 Bageshwar 2009-10 to 2018-19 Approved   The posting of WPO is awaited
12 Civil Soyam Almora 2009-10 to 2018-19 Approved   The posting of WPO is awaited
13 Mussoorie 2011-12 to 2020-21 Approved    
14 Upper Yamuna Barkot 2011-12 to 2020-21 Approved    
15 Haridwar 2011-12 to 2020-21 Approved    
16 Pithoragarh 2011-12 to 2020-21 Approved    
17 Champawat 2011-12 to 2020-21 Approved    
18 Garhwal 2011-12 to 2020-21 Approved    
19 Kedarnath Wildlife Division 2004-05 to 2013-14 Expired   Draft WP(2014-15 to 2023-24 ) submitted to GoI & circulated to all members of Standing Consultative Committee for their comments

Nandadevi National Park 
First Time   Draft WP(2014-15 to 2023-24 ) submitted to GoI & circulated to all members of Standing Consultative Committee for their comments
20 Narendranagar 2013-14 to 2022-23 Approved    
21 Tehri 2014-15 to 2023-24 Approved    
22 Badrinath 2014-15 to 2023-24 Approved    
23 Lansdowne 2014-15 to 2023-24 Approved    

Lansdowne Cantt 2014-15 to 2023-24 Submitted to GoI   WP submitted to GoI for approval
24 Rudraprayag 2014-15 to 2023-24 Approved    
25 Tarai Central 2015-16 to 2024-25 Approved    
26 Tarai West 2015-16 to 2024-25 Approved    